Wendy Bisaro
Statements in Debates
Thank you, committee. We’ll move to page 11-8, 11-9, activity summary, forest management, infrastructure investment summary, total infrastructure investment summary, $1.510 million. Mr. Hawkins.
Thank you, Mr. Speaker. As you heard from Mr. Bromley already, for a full week this past September the environmental assessment hearings were held on the remediation plan for the Giant Mine site. The GNWT is a partner with the Government of Canada, acting as the developer for the project at these hearings. Two weeks ago the developer made their final submission to the Mackenzie Valley Environmental Impact Review Board, and reading the content of their submission, as Mr. Bromley stated, I also felt that it’s almost as though they weren’t listening to any of the presenters.
The GNWT...
Thank you, Mr. Speaker. Your committee has been considering Tabled Document 64-17(3), Northwest Territories Capital Estimates 2013-2014, and would like to report progress with one motion being adopted, that consideration of Tabled Document 64-17(3) is concluded, and that the House concur in those estimates and that an appropriation bill to be based thereon be introduced without delay. Mr. Speaker, I move that the report of Committee of the Whole be concurred with. Thank you.
Does committee agree we will proceed without witnesses?
Question has been called.
---Carried
Thank you, committee. What is the wish of committee? Mr. Menicoche.
Okay, committee, we will go back to the department summary, page 10-2, department summary, infrastructure investment summary, total infrastructure investment summary, $2.060 million. Is committee agreed we are concluded with the Department of Industry, Tourism and Investment?
Thank you, committee. Mr. Menicoche.
Some of them are… That’s good. Welcome, witnesses. Mr. Ramsay, if you would introduce your witnesses for the record, please.
Is committee agreed we are concluded the department… Oh, do we have one more? Oh, yes. We need to return to page 11-2, department summary, infrastructure investment summary, total infrastructure investment summary, $1.861 million.
I will call Committee of the Whole back to order. Committee, we are beginning the Department of Industry, Tourism and Investment. We are on page 10-2. Industry, Tourism and Investment, department summary, infrastructure investment summary, total infrastructure investment summary, $2.060 million. We will defer this page until we have covered the various sections. We will move to page 10-4. Industry, Tourism and Investment, activity summary, tourism and parks, infrastructure investment summary, total infrastructure investment summary, $2.060 million. I will go to the Minister of Industry...