Katrina Nokleby

Katrina Nokleby
Great Slave

Statements in Debates

Debates of , 19th Assembly, 2nd Session (day 111)

Thank you, Mr. Speaker. Mr. Speaker, I'm not going to spend any time here today rehashing the items that are in the budget and what aren't. I've sort of sat down to formulate my thoughts over the last week or so and really thought my best bet would be to get up to speak from my heart because that is where I am what I am using to make my decision.

One thing that I have really learned over the last three years now in this role or almost three years is that we are only as strong as our weakest community and that until we start to build up the small communities and all of our residents in need...

Debates of , 19th Assembly, 2nd Session (day 111)

In favour.

Debates of , 19th Assembly, 2nd Session (day 111)

Thank you, Mr. Speaker. I think the Minister misunderstood me. I actually don't want her at the meetings. I was asking about the technical staff, the lower level. It is my understanding that only high level meetings are occurring at this point. And as we need to have this lift of material go down this year, does the Minister commit to directing her department to find the money to start the lift this year? Thank you.

Debates of , 19th Assembly, 2nd Session (day 111)

(Audio)

Debates of , 19th Assembly, 2nd Session (day 111)

Thank you, Mr. Speaker. Mr. Speaker, my questions are for the Minister of Infrastructure. Does the Minister understand the difference between a joint venture and an Indigenous government? Thank you, Mr. Speaker.

Debates of , 19th Assembly, 2nd Session (day 111)

Thank you, Mr. Speaker. Mr. Speaker, has the department met with the JV since February 7th when their proposal was submitted? Thank you.

Debates of , 19th Assembly, 2nd Session (day 111)

Against.

Debates of , 19th Assembly, 2nd Session (day 111)

Thank you, Mr. Speaker. My questions are for the Minister of Infrastructure regarding the Inuvik Airport.

When I hear the Minister say that the delay at this point is around funding, I find myself quite confused considering the announcement of $150 million was made in 2019. Can the Minister speak to why the conversation about funding, particularly when we would be breaking this project up into phases and different work packages, would be waiting as of now two years three years later. Thank you, Mr. Speaker.

Debates of , 19th Assembly, 2nd Session (day 111)

In favour.

Debates of , 19th Assembly, 2nd Session (day 111)

Thank you, Mr. Speaker. Mr. Speaker, I’d like to provide some clarity around the issues at the Inuvik Airport. Media has reported that the need to dig a trench is the issue; however, it appears upon further investigation this is not correct. The real issue with the airport project and why a delay now could cost this construction year has to do with the permafrost our coldhearted friend that causes so many headaches for engineers and contractors in the North.

Due to ground conditions, construction of the runway expansion in Inuvik requires that the design and construction factor in the...