Debates of , 19th Assembly, 2nd Session (day 158)

No. That's great news. I will ask in August how much the fire centre is going to cost. The people of Fort Smith, I think will be happy, that some amount of money is being spent in their community. Thank you.

Debates of , 19th Assembly, 2nd Session (day 158)

Yeah, thank you, Mr. Speaker. I recognize that when there's contractor litigation that, you know, we don't quite know that. I guess I'm looking for a commitment that at some point the housing could release some public information on this. What we often do is we sign NDAs and we add a few more million dollars on to the project and then no one will say anything about that. And it's happened many times in this Assembly, and I would not want this to be a case. I think it is a project that is - the Minister said there are lessons learned. I would like to see what those lessons learned. And I think...

Debates of , 19th Assembly, 2nd Session (day 158)

I mean, I somewhat disagree with that. You are asking the Assembly for millions of dollars; you can probably also ask the feds for millions of dollars. Do we have an estimated date of completion for the Fort Smith Territorial Fire Centre? Thank you.

Debates of , 19th Assembly, 2nd Session (day 158)

Thank you, Mr. Speaker. My questions are for the Minister responsible for housing. Can the Minister tell us when the Fort Good Hope Seniors Centre is going to open? Thank you.

Debates of , 19th Assembly, 2nd Session (day 158)

Yeah, thank you, Madam Chair. Can I just get a bit more understanding, then, of how this is going to be procured. Will this be normal public procurement, and then I guess the intention is this $1.6 million will be intended to get us design and then we will go out for a public tender? Is this a design bid built essentially, I'm asking, or a design build; what kind of procurement are we using? Thank you.

Debates of , 19th Assembly, 2nd Session (day 158)

Yeah, thank you, Madam Chair. You know, it's obviously in everyone's interest to spend this tens of millions of dollars, I think. We've heard the feds say, you know, well we don't need to give you more community infrastructure money, you're not spending the money we gave you. And I've heard MACA say similarly well, we don't need to increase the community infrastructure budget, there's tens of millions of dollars not being spent. I think we all know if this was just unconditional money to spend on infrastructure, they'd get it done. But sometimes the ICIP project categories were rather specific...

Debates of , 19th Assembly, 2nd Session (day 158)

Yeah, thank you, Madam Chair. I guess my concern is the way I understand this to work is the feds essentially gave us $66 million, they said, get your communities to apply and then you will help decide which ones go forward, not all of the projects communities wanted to do obviously made the first round of cuts and now there are some that, you know, inflation is causing some community needs to reapply or find other money or not go ahead so that money is not available for another community to kind of fill in the gap. That's my understanding of the current situation. So I guess the solution...

Debates of , 19th Assembly, 2nd Session (day 158)

Thank you, Madam Chair. This is $29 million being carried over although we are holding approximately $66 million, and I believe there's actually quite a bit more through some other ICIP funding for municipalities. I believe all of this money has been allocated. It's project specific so a community worked with us to apply to the feds and we'll build X thing. But my understanding is, and we got - we weren't going to get all that money out so we asked the feds for an extension, they gave us an extension, but my understanding is that quite a bit of these allocated projects are now at the state...

Debates of , 19th Assembly, 2nd Session (day 158)

Thank you. That was very helpful in helping me understand why I have $54 million and we have $2.7 million. I appreciate that. I guess what this also leads me into is, is there any hope of publishing some sort of capital plan? You know, I know we have a capital acquisition plan, I know we have a capital needs assessment that goes, I believe, ten years, maybe even 30 years. I know the Department of Infrastructure has another plan with deferred maintenance and things in it. But there's nowhere I can look to kind of see what the GNWT has in the lineup and what it's planning to build. You have to...

Debates of , 19th Assembly, 2nd Session (day 158)

Yeah. Yeah, thank you, Madam Chair. Maybe I had a different number in my head. I guess, sorry, can I clarify, then, would that - that's the first time I heard that number. Would that be, like, a licensing fee? Has something changed in the sense that it would be $370,000 annually or, yeah, can I just get some more context. Is that total, we get some custom designed software and we own it kind of thing? Thank you.